10/12/2021: All States Construction is planning to start installing the base gravel on Carding Machine Road on or about October 18th. At the same time, they plan to start the box cuts and installation of the subbase gravel on Dingley Road, followed by the base gravel when they have completed Carding Machine Road. Once the base work is complete, the paving will be scheduled.
10/08/2021: Aceto and Sons Earthwork will be removing pavement and installing base pavement on Tuesday, October 12th. Then Lower Main Street will be closed on Thursday, October 14th for paving.